Crews in China Complete World's Longest Steel-Reinforced Concrete Arch Bridge

作者:Aileen Cho     編輯:賈琦艷     來源:Engineering News-Record   發表于: 2024-08-09 13:09  點擊:

https://www.enr.com/articles/58835-crews-in-china-complete-worlds-longest-steel-reinforced-concrete-arch-bridge


Longtan Bridge currently holds the long-span record for bridges of its type.

Photo courtesy of Man-Chung Tang/TYLI



Crews in Guangxi, China are wrapping up punch-list items and dismantling the project site of what is now the world’s longest steel-reinforced concrete arch bridge. The Tian’e Longtan Bridge, with a 600-meter main span, beats out the Third PingNan Bridge by 25 m.

Contractor Guangxi Road and Bridge Engineering Group Co., Ltd. (GRBG) began building the approximately 2,500-m-long bridge in 2020 as part of the Nandan-to-Tian'e Expressway through the mountainous region of Tian'e County.

The bridge crosses a reservoir over the Hongshuihe River that is up to 900 m wide and approximately 130 m deep, according to a report by the contractor provided to ENR. The bridge deck rises 140 m over the reservoir.

The box-ribbed, steel-tubed arch structure, supported by 13 horizontal struts, carries four lanes of traffic. Crews utilized a cantilever construction method using stay cables without any falsework support—a method developed by bridge designer Jielian Zheng in 1968. According to a technical paper he wrote at Guangxi University, China has more than 300 arch bridges built this way, Zheng said. The T-shaped prestressed concrete girders have spans of 40 m.

The five longest arch bridges in the world all are located in China, notes Man-Chung Tang, chairman of T.Y. Lin International’s China branch, and an advisor on the project.

“An arch can support itself only after the entire arch rib is complete,” Tang says. “In the old days, the ribs of an arch bridge had to be completely supported by shuttering or formwork during construction before the entire arch rib was fully completed and the abutments were poured. This limited the spans of the arches we could build because the formwork would otherwise be too expensive and less stable. Very long-span arch bridges became possible only after Prof. Zheng developed this cable-stayed method for arch construction. In addition, he developed methods to ascertain that the concrete inside the steel tubes be fully attached to the steel shell.”

Evolving technologies, such as vacuum-assisted graded pumping, non-shrinkage concrete and instantaneous stress load regulation of arch rings also enabled the 600-m span, according to the contractor.

The bridge’s steel “skeleton” is 8,200 tons and divided into 44 segments. The biggest segment is 23.35 m long, 9.91 m high and 5.2 m wide. “After careful search, we found an abandoned soil disposal site, approximately 60,000 cu meters in size,” that became a steel fabrication plant, according to the contractor. “Moreover, it is located near the river, making it convenient to hoist these segments onto large ships.”

Access to the site was a challenge. “In terms of land transportation, there is a connection to a secondary road 16 km away via rural paths on one bank,” according to the contractor. “On the other bank, the rural paths that connect to the nearest secondary road are approximately 35 km away, with an elevation difference of about 100 m, making it practically unusable.”

Crews upgraded the paths on the first bank and built docks on both banks to accommodate material and equipment transportation.

In his paper, Zheng says technologies must continue to advance to increase arch span lengths. They include the need to “improve the fatigue resistance of welded joints; to study a more convenient connection between hanging sections … a new calculation method of section-bearing capacity and [a] rapid construction method are studied.”

He added, “At present, we have demonstrated the feasibility of the concrete-filled steel tube arch bridge with a net span of 700 m, and look forward to the concrete arch bridge with a span of more than 700 m as soon as possible.”

KEYWORDS: Arch bridgesbridge constructionJielian ZhengLongtan Bridge

 

編輯:賈琦艷

上一條:賦能新質生產力發展?第二十一屆全國機械工程學院院長/系主任聯席會議在南寧召開

下一條:全國機械工程學院院長/系主任聚邕交流


巴楚县| 百家乐免费试玩| 华硕百家乐的玩法技巧和规则| e娱乐城棋牌| 娱乐城百家乐官网可以代理吗| 澳门百家乐是骗人的| 回力百家乐官网的玩法技巧和规则 | 威尼斯人娱乐网代理| 百家乐官网过两关| 威尼斯人娱乐场钓鱼网站| 迪威百家乐官网娱乐场| bet365金融| 百家乐娱乐城博彩正网| 雷波县| 带百家乐的时时彩平台| 灌云县| 粤港澳百家乐娱乐网| 百家乐官网筹码500| 澳门百家乐有没有假| 宝马会百家乐官网现金网| 百家乐投注网出租| 土豪百家乐的玩法技巧和规则| 机率游戏| 大发888国际娱乐城lm0| 太阳城房价| 百家乐金海岸软件| 中国百家乐官网游戏| 百家乐官网1326投注| 巴西百家乐的玩法技巧和规则 | 和林格尔县| 赌百家乐大小点桌| 百家乐官网娱乐用品| bet365怎么上不去| 百家乐园鼎丰娱乐城| 百家乐官网的桌布| 仪陇县| 百家乐赢钱面面观| 百家乐官网娱乐城体验金| 百家乐官网视频挖坑| 百家乐官网双龙出海注码法| 一共33楼24楼风水怎么说|